25INR0329 · BESS · Nueces County
Lynx Energy Storage
Lynx Energy Storage is a 125 MW battery storage project in Nueces County, Texas, connecting at 138KV Tap 8921 Terra Verde - 8518 Kingsville. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 05/01/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0329
- Capacity
- 125 MW
- Fuel
- BESS (BA)
- County
- Nueces County
- Interconnecting entity
- Corpus Battery Storage, LLC
- Projected COD
- 05/01/2026
- Entered queue
- 03/01/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/07/2026Energization Approved → Sync Approved
- 03/19/2026IA Signed → Energization Approved
- 08/22/2025FIS Requested → FIS Approved
- 04/09/2024FIS Approved → IA Signed
- 03/01/2023Entered the queue with 125 MW, projected COD 05/01/2026
- 03/01/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.