1 active project totalling 600 MW is queued to connect at Tap 345kV 59904 Cottonwood–60500 Edith Clarke in Motley County, Texas, according to ERCOT's October 2026 report.

Active capacity
600 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0017Sitges WindWind600FIS Requested03/31/20300