28INR0017 · Wind · Motley County
Sitges Wind
Sitges Wind is a 600 MW wind project in Motley County, Texas, connecting at Tap 345kV 59904 Cottonwood–60500 Edith Clarke. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0017
- Capacity
- 600 MW
- Fuel
- Wind (WT)
- County
- Motley County
- Interconnecting entity
- Whistling Flats Wind, LLC
- Projected COD
- 03/31/2030
- Entered queue
- 02/29/2024
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/29/2024Entered the queue with 600 MW, projected COD 03/31/2030
- 02/29/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.