Substation / point of interconnection · Mills County
tap the 138 kV Goldthwaite (#7070) – San Saba Switch (#77074)
1 active project totalling 131 MW is queued to connect at tap the 138 kV Goldthwaite (#7070) – San Saba Switch (#77074) in Mills County, Texas, according to ERCOT's October 2026 report.
Active capacity
131 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0105 | Starlight Solar | Solar | 131 | IA Signed | 05/09/2030 | 0 |