Substation / point of interconnection · Milam County
Tap 138kV Thorndale North (bus #3659) – Rookie Switch (bus #3701)
1 active project totalling 232 MW is queued to connect at Tap 138kV Thorndale North (bus #3659) – Rookie Switch (bus #3701) in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
232 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0502 | Adelite Storage | BESS | 232 | IA Signed | 04/20/2028 | 1 |