LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0502 · BESS · Milam County

Adelite Storage

COD delayed 1×

Adelite Storage is a 232 MW battery storage project in Milam County, Texas, connecting at Tap 138kV Thorndale North (bus #3659) – Rookie Switch (bus #3701). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/20/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0502
Capacity
232 MW
Fuel
BESS (BA)
Interconnecting entity
Adelite Storage Project LLC
Projected COD
04/20/2028
Entered queue
06/27/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 06/28/2027 → 04/20/2028 (+10 months)
  • 08/27/2024
    FIS Approved → IA Signed
  • 05/01/2024
    FIS Requested → FIS Approved
  • 09/09/2022
    Screening → FIS Requested
  • 06/27/2022
    Entered the queue with 232 MW, projected COD 06/28/2027

Other projects at this substation

No other projects at this substation.