Substation / point of interconnection ยท Mclennan County
Tap 345kV 3405 THOUSE__5 - 3406 ELM_MOTT_5
1 active project totalling 121 MW is queued to connect at Tap 345kV 3405 THOUSE__5 - 3406 ELM_MOTT_5 in Mclennan County, Texas, according to ERCOT's October 2026 report.
Active capacity
121 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0380 | Pepper Solar Farm | Solar | 121 | IA Signed | 09/20/2027 | 0 |