LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Mclennan County

345 kV Tiger Creek Switch (#3379)

1 active project totalling 307 MW is queued to connect at 345 kV Tiger Creek Switch (#3379) in Mclennan County, Texas, according to ERCOT's October 2026 report.

Active capacity
307 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0157Axtell BESSBESS307FIS Requested04/16/20290