Substation / point of interconnection ยท Mclennan County
345 kV Tiger Creek Switch (#3379)
1 active project totalling 307 MW is queued to connect at 345 kV Tiger Creek Switch (#3379) in Mclennan County, Texas, according to ERCOT's October 2026 report.
Active capacity
307 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0157 | Axtell BESS | BESS | 307 | FIS Requested | 04/16/2029 | 0 |