Substation / point of interconnection ยท Matagorda County
Blessing Substation 138 kV (ID 8121)
1 active project totalling 154 MW is queued to connect at Blessing Substation 138 kV (ID 8121) in Matagorda County, Texas, according to ERCOT's October 2026 report.
Active capacity
154 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0341 | Bastion BESS | BESS | 154 | FIS Requested | 11/01/2028 | 0 |