28INR0341 · BESS · Matagorda County
Bastion BESS
Bastion BESS is a 154 MW battery storage project in Matagorda County, Texas, connecting at Blessing Substation 138 kV (ID 8121). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0341
- Capacity
- 154 MW
- Fuel
- BESS (BA)
- Substation
- Blessing Substation 138 kV (ID 8121)
- County
- Matagorda County
- Interconnecting entity
- BESS BASTION LLC
- Projected COD
- 11/01/2028
- Entered queue
- 06/19/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/19/2025Entered the queue with 154 MW, projected COD 11/01/2028
- 06/19/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.