ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Leon County

(PSSE BUS# 47) HILTOPLKS8 138kV

1 active project totalling 157 MW is queued to connect at (PSSE BUS# 47) HILTOPLKS8 138kV in Leon County, Texas, according to ERCOT's October 2026 report.

Active capacity
157 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0092Pecan BESSBESS157FIS Approved12/31/20280