27INR0092 · BESS · Leon County

Pecan BESS

Pecan BESS is a 157 MW battery storage project in Leon County, Texas, connecting at (PSSE BUS# 47) HILTOPLKS8 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0092
Capacity
157 MW
Fuel
BESS (BA)
Interconnecting entity
Gransolar Texas Three LLC
Projected COD
12/31/2028
Entered queue
10/12/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/29/2025
    FIS Requested → FIS Approved
  • 10/12/2023
    Entered the queue with 157 MW, projected COD 12/31/2028
  • 10/12/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.