Substation / point of interconnection · Lamar County
Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693)
2 active projects totalling 223 MW are queued to connect at Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693) in Lamar County, Texas, according to ERCOT's October 2026 report.
Active capacity
223 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0225 | MRG GOODY SOLAR | Solar | 171 | Sync Approved | 08/28/2026 | 0 |
| 24INR0305 | MRG Goody Storage | BESS | 52 | Sync Approved | 08/28/2026 | 0 |