Substation / point of interconnection ยท Kaufman County
Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)
2 active projects totalling 300 MW are queued to connect at Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432) in Kaufman County, Texas, according to ERCOT's October 2026 report.
Active capacity
300 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0303 | Erika Solar | Solar | 200 | Sync Approved | 11/25/2026 | 0 |
| 27INR0531 | Erika BESS | BESS | 100 | FIS Requested | 07/01/2029 | 0 |