LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0531 · BESS · Kaufman County

Erika BESS

Erika BESS is a 100 MW battery storage project in Kaufman County, Texas, connecting at Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0531
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
Erika Solar, LLC
Projected COD
07/01/2029
Entered queue
06/06/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/06/2025
    Entered the queue with 100 MW, projected COD 07/01/2029
  • 06/06/2025
    Screening → FIS Requested

Other projects at this substation

Erika SolarSolar200 MWSync Approved