Substation / point of interconnection ยท Jones County
existing tap 345 kV 68004 Phantom Hill station
1 active project totalling 201 MW is queued to connect at existing tap 345 kV 68004 Phantom Hill station in Jones County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 20INR0242 | Anson Solar 2 | Solar | 201 | Sync Approved | 10/01/2026 | 0 |