20INR0242 · Solar · Jones County
Anson Solar 2
Anson Solar 2 is a 201 MW solar project in Jones County, Texas, connecting at existing tap 345 kV 68004 Phantom Hill station. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/01/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0242
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Jones County
- Interconnecting entity
- Anson Solar Center 2, LLC
- Projected COD
- 10/01/2026
- Entered queue
- 06/23/2017
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/25/2025Energization Approved → Sync Approved
- 11/04/2025IA Signed → Energization Approved
- 03/19/2025FIS Requested → FIS Approved
- 08/15/2024FIS Approved → IA Signed
- 02/15/2018Screening → FIS Requested
- 06/23/2017Entered the queue with 201 MW, projected COD 10/01/2026
Other projects at this substation
No other projects at this substation.