Substation / point of interconnection ยท Hill County
tap 345kV 68090 Sam Switch - 1907 Venus
1 active project totalling 406 MW is queued to connect at tap 345kV 68090 Sam Switch - 1907 Venus in Hill County, Texas, according to ERCOT's October 2026 report.
Active capacity
406 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0023 | Compadre Solar | Solar | 406 | Sync Approved | 10/31/2026 | 1 |