24INR0023 · Solar · Hill County
Compadre Solar
COD delayed 1×
Compadre Solar is a 406 MW solar project in Hill County, Texas, connecting at tap 345kV 68090 Sam Switch - 1907 Venus. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/31/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0023
- Capacity
- 406 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 68090 Sam Switch - 1907 Venus
- County
- Hill County
- Interconnecting entity
- Hill Solar I, LLC
- Projected COD
- 10/31/2026
- Entered queue
- 03/08/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 07/31/2026 → 10/31/2026 (+3 months)
- 11/13/2024Energization Approved → Sync Approved
- 10/30/2024IA Signed → Energization Approved
- 01/31/2024FIS Requested → FIS Approved
- 11/12/2022FIS Approved → IA Signed
- 03/08/2021Entered the queue with 406 MW, projected COD 07/31/2026
- 03/08/2021Screening → FIS Requested