Substation / point of interconnection ยท Hidalgo County
Tap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01
1 active project totalling 168 MW is queued to connect at Tap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01 in Hidalgo County, Texas, according to ERCOT's October 2026 report.
Active capacity
168 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0205 | Donna Solar | Solar | 168 | FIS Requested | 02/22/2029 | 0 |