LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0205 · Solar · Hidalgo County

Donna Solar

Donna Solar is a 168 MW solar project in Hidalgo County, Texas, connecting at Tap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/22/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0205
Capacity
168 MW
Fuel
Solar (PV)
Interconnecting entity
Donna Solar LLC
Projected COD
02/22/2029
Entered queue
03/22/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/06/2024
    Screening → FIS Requested
  • 03/22/2024
    Entered the queue with 168 MW, projected COD 02/22/2029

Other projects at this substation

No other projects at this substation.