LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Harris County

Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820)

1 active project totalling 201 MW is queued to connect at Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820) in Harris County, Texas, according to ERCOT's October 2026 report.

Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0343Stinger Energy StorageBESS201FIS Requested03/01/20280