LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0343 · BESS · Harris County

Stinger Energy Storage

Stinger Energy Storage is a 201 MW battery storage project in Harris County, Texas, connecting at Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0343
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Stinger Energy Storage LLC
Projected COD
03/01/2028
Entered queue
11/02/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/02/2023
    Entered the queue with 201 MW, projected COD 03/01/2028
  • 11/02/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.