Substation / point of interconnection ยท Harris County
44140 CLODINE 138kV
1 active project totalling 165 MW is queued to connect at 44140 CLODINE 138kV in Harris County, Texas, according to ERCOT's October 2026 report.
Active capacity
165 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0584 | Kegans BESS (Houston IV BESS) | BESS | 165 | Sync Approved | 09/05/2026 | 0 |