24INR0584 · BESS · Harris County
Kegans BESS (Houston IV BESS)
Kegans BESS (Houston IV BESS) is a 165 MW battery storage project in Harris County, Texas, connecting at 44140 CLODINE 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/05/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0584
- Capacity
- 165 MW
- Fuel
- BESS (BA)
- Substation
- 44140 CLODINE 138kV
- County
- Harris County
- Interconnecting entity
- SMT Houston IV LLC
- Projected COD
- 09/05/2026
- Entered queue
- 06/27/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/08/2026Energization Approved → Sync Approved
- 05/06/2026IA Signed → Energization Approved
- 07/01/2025FIS Requested → FIS Approved
- 11/07/2024FIS Approved → IA Signed
- 06/27/2023Entered the queue with 165 MW, projected COD 09/05/2026
- 06/27/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.