Substation / point of interconnection ยท Harris County
42360 Mirage POI 8 138kV
1 active project totalling 26 MW is queued to connect at 42360 Mirage POI 8 138kV in Harris County, Texas, according to ERCOT's October 2026 report.
Active capacity
26 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0345 | NET Power Demonstration plant | Gas | 26 | FIS Approved | 08/21/2027 | 0 |