26INR0345 · Gas · Harris County
NET Power Demonstration plant
NET Power Demonstration plant is a 26 MW natural gas project in Harris County, Texas, connecting at 42360 Mirage POI 8 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 08/21/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0345
- Capacity
- 26 MW
- Fuel
- Gas (GT)
- Substation
- 42360 Mirage POI 8 138kV
- County
- Harris County
- Interconnecting entity
- NET Power LLC
- Projected COD
- 08/21/2027
- Entered queue
- 12/20/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/10/2025FIS Requested → FIS Approved
- 09/03/2024Screening → FIS Requested
- 12/20/2023Entered the queue with 26 MW, projected COD 08/21/2027