2 active projects totalling 813 MW are queued to connect at 23920 Blackwater 345kV in Hale County, Texas, according to ERCOT's October 2026 report.

Active capacity
813 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
22INR0462Old Aqueduct SolarSolar512FIS Requested06/01/20280
22INR0330Old Aqueduct BattBESS301FIS Requested03/01/20300