22INR0462 · Solar · Hale County
Old Aqueduct Solar
Old Aqueduct Solar is a 512 MW solar project in Hale County, Texas, connecting at 23920 Blackwater 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0462
- Capacity
- 512 MW
- Fuel
- Solar (PV)
- Substation
- 23920 Blackwater 345kV
- County
- Hale County
- Interconnecting entity
- Old Aqueduct Solar
- Projected COD
- 06/01/2028
- Entered queue
- 12/03/2020
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/29/2021Screening → FIS Requested
- 12/03/2020Entered the queue with 512 MW, projected COD 06/01/2028
Other projects at this substation
| Old Aqueduct Batt | BESS | 301 MW | FIS Requested |