2 active projects totalling 406 MW are queued to connect at tap 345kV 5133 Elm Creek - 5915 STP ckt 1 in Guadalupe County, Texas, according to ERCOT's October 2026 report.
Active capacity
406 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0007 | Nockenut Springs Solar 2 | Solar | 203 | IA Signed | 06/05/2029 | 0 |
| 23INR0088 | Nockenut Springs Solar 1 | Solar | 203 | IA Signed | 06/05/2029 | 0 |