Substation / point of interconnection ยท Grayson County
Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch
1 active project totalling 570 MW is queued to connect at Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch in Grayson County, Texas, according to ERCOT's October 2026 report.
Active capacity
570 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0108 | RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) | Gas | 570 | IA Signed | 02/26/2028 | 0 |