28INR0108 · Gas · Grayson County
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) is a 570 MW natural gas project in Grayson County, Texas, connecting at Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/26/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0108
- Capacity
- 570 MW
- Fuel
- Gas (GT)
- Substation
- Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch
- County
- Grayson County
- Interconnecting entity
- Rayburn Country Electric Cooperative, Inc.
- Projected COD
- 02/26/2028
- Entered queue
- 01/02/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/22/2025FIS Requested → IA Signed
- 01/02/2025Entered the queue with 570 MW, projected COD 02/26/2028
- 01/02/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.