Substation / point of interconnection ยท Goliad County
The Coleto Greek (#8164) to Pawnee Switching Station (#5725) ; LCRA
1 active project totalling 314 MW is queued to connect at The Coleto Greek (#8164) to Pawnee Switching Station (#5725) ; LCRA in Goliad County, Texas, according to ERCOT's October 2026 report.
Active capacity
314 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0149 | Diablo Campo Storage | BESS | 314 | FIS Requested | 09/30/2029 | 0 |