ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0149 · BESS · Goliad County

Diablo Campo Storage

Diablo Campo Storage is a 314 MW battery storage project in Goliad County, Texas, connecting at The Coleto Greek (#8164) to Pawnee Switching Station (#5725) ; LCRA. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0149
Capacity
314 MW
Fuel
BESS (BA)
Interconnecting entity
Diablo Campo Energy Center, LLC
Projected COD
09/30/2029
Entered queue
01/23/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/23/2024
    Entered the queue with 314 MW, projected COD 09/30/2029
  • 01/23/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.