Substation / point of interconnection ยท Ector County
Tap 345kv line Wolf BUS# 11010 - Reiter BUS#18544
1 active project totalling 503 MW is queued to connect at Tap 345kv line Wolf BUS# 11010 - Reiter BUS#18544 in Ector County, Texas, according to ERCOT's October 2026 report.
Active capacity
503 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0205 | Gypsum Plains Solar | Solar | 503 | FIS Requested | 06/21/2029 | 0 |