Gypsum Plains Solar is a 503 MW solar project in Ector County, Texas, connecting at Tap 345kv line Wolf BUS# 11010 - Reiter BUS#18544. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/21/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0205
Capacity
503 MW
Fuel
Solar (PV)
Interconnecting entity
Gypsum Plains Solar, LLC
Projected COD
06/21/2029
Entered queue
05/29/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/29/2025
    Entered the queue with 503 MW, projected COD 06/21/2029
  • 05/29/2025
    Screening → FIS Requested