LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Colorado County

L_GLIDDE8_1Y; Bus number - 7258 138KV

1 active project totalling 184 MW is queued to connect at L_GLIDDE8_1Y; Bus number - 7258 138KV in Colorado County, Texas, according to ERCOT's October 2026 report.

Active capacity
184 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0555Montezuma StorageBESS184FIS Requested10/16/20300