27INR0555 · BESS · Colorado County

Montezuma Storage

Montezuma Storage is a 184 MW battery storage project in Colorado County, Texas, connecting at L_GLIDDE8_1Y; Bus number - 7258 138KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/16/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0555
Capacity
184 MW
Fuel
BESS (BA)
Interconnecting entity
Montezuma Storage LLC
Projected COD
10/16/2030
Entered queue
09/04/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/04/2025
    Entered the queue with 184 MW, projected COD 10/16/2030
  • 09/04/2025
    Screening → FIS Requested