1 active project totalling 80 MW is queued to connect at Tap 138kV 59450 Waterport Substation - 5789 Southmost Sub in Cameron County, Texas, according to ERCOT's October 2026 report.
Active capacity
80 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0515 | Rio Grand Valley Element Fuels Power | Other | 80 | FIS Requested | 12/05/2028 | 0 |