Substation / point of interconnection ยท Cameron County
8626 Resaca 69kV
1 active project totalling 25 MW is queued to connect at 8626 Resaca 69kV in Cameron County, Texas, according to ERCOT's October 2026 report.
Active capacity
25 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0319 | Burro Loco Energy Storage | BESS | 25 | FIS Requested | 09/15/2028 | 0 |