Substation / point of interconnection ยท Cameron County

80229 Cavazos 138kV

1 active project totalling 252 MW is queued to connect at 80229 Cavazos 138kV in Cameron County, Texas, according to ERCOT's October 2026 report.

Active capacity
252 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
22INR0401Eval StorageBESS252IA Signed04/30/20290