Substation / point of interconnection ยท Cameron County
(#79501) Kingfisher 345 kV
1 active project totalling 1,536 MW is queued to connect at (#79501) Kingfisher 345 kV in Cameron County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,536 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0084 | Aegle Power | Gas | 1,536 | FIS Requested | 07/30/2027 | 0 |