Substation / point of interconnection ยท Cameron County
79500 Palmito 345kV
3 active projects totalling 603 MW are queued to connect at 79500 Palmito 345kV in Cameron County, Texas, according to ERCOT's October 2026 report.
Active capacity
603 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0427 | Ouroboros Grid BESS 4 | BESS | 201 | Screening | 06/01/2029 | 0 |
| 28INR0428 | Ouroboros Grid BESS 5 | BESS | 201 | Screening | 06/01/2029 | 0 |
| 28INR0429 | Ouroboros Grid BESS 6 | BESS | 201 | Screening | 06/01/2029 | 0 |