LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Brown County

Tap 345 kV 1444 BROWN SWITCH - 3424 BUCKHORN SWITCH

2 active projects totalling 298 MW are queued to connect at Tap 345 kV 1444 BROWN SWITCH - 3424 BUCKHORN SWITCH in Brown County, Texas, according to ERCOT's October 2026 report.

Active capacity
298 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0331Chisme StorageBESS151FIS Approved04/13/20270
24INR0333Chisme SolarSolar147FIS Approved04/13/20270