Substation / point of interconnection ยท Brazoria County
39030 TNMP Alvin 138kV
0 active projects totalling 0 MW are queued to connect at 39030 TNMP Alvin 138kV in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
0 MW
queued at this substation
Active projects
0
1 project ever listed
Withdrawn share EST
100%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0706 | Bocanova Power II | BESS | 150 | Withdrawn | 08/31/2026 | 0 |