Substation / point of interconnection ยท Bexar County
Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465)
1 active project totalling 232 MW is queued to connect at Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465) in Bexar County, Texas, according to ERCOT's October 2026 report.
Active capacity
232 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0479 | Taormina Storage | BESS | 232 | IA Signed | 05/26/2029 | 0 |