23INR0479 · BESS · Bexar County

Taormina Storage

Taormina Storage is a 232 MW battery storage project in Bexar County, Texas, connecting at Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/26/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0479
Capacity
232 MW
Fuel
BESS (BA)
Interconnecting entity
Taormina Storage Project LLC
Projected COD
05/26/2029
Entered queue
04/18/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/14/2025
    FIS Requested → IA Signed
  • 10/26/2022
    Screening → FIS Requested
  • 04/18/2022
    Entered the queue with 232 MW, projected COD 05/26/2029

Other projects at this substation

No other projects at this substation.