Substation / point of interconnection ยท Bastrop County
7560 RED ROCK 138kV
1 active project totalling 203 MW is queued to connect at 7560 RED ROCK 138kV in Bastrop County, Texas, according to ERCOT's October 2026 report.
Active capacity
203 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0514 | Techne BESS | BESS | 203 | FIS Requested | 12/31/2028 | 0 |