26INR0514 · BESS · Bastrop County
Techne BESS
Techne BESS is a 203 MW battery storage project in Bastrop County, Texas, connecting at 7560 RED ROCK 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0514
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- Substation
- 7560 RED ROCK 138kV
- County
- Bastrop County
- Interconnecting entity
- Techne BESS, LLC
- Projected COD
- 12/31/2028
- Entered queue
- 09/05/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/05/2024Entered the queue with 203 MW, projected COD 12/31/2028
- 09/05/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.