30INR0002 · Other · Lamar County
Southeast Oklahoma Pumped Storage
Southeast Oklahoma Pumped Storage is a 1,232 MW other project in Lamar County, Texas, connecting at 1692 Paris Switch 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/01/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0002
- Capacity
- 1,232 MW
- Fuel
- Other (OT)
- Substation
- 1692 Paris Switch 345kV
- County
- Lamar County
- Interconnecting entity
- Apex Energy Solutions, LLC
- Projected COD
- 01/01/2030
- Entered queue
- 08/05/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/10/2023Screening → FIS Requested
- 08/05/2022Entered the queue with 1,232 MW, projected COD 01/01/2030